Sprint Truth for Jira

← Guides

Sprint report export with the added-after-start asterisk

Examples use made-up data: the Payments team, Sprint 42, PAY-212.

Jira's Sprint Report can't be exported with its asterisk. People copy it into spreadsheets by hand.

With Sprint Truth

  1. Search for the sprint, including removed work items:
    Sprints = "Sprint 42"
  2. Add the columns Added after start, Removed from, Times carried over and Story points.
  3. Use Jira's Export → CSV.

In the spreadsheet, a work item was added after the start if "Sprint 42" appears in its Added after start column.

Sprint Truth doesn't copy Jira's Sprint Report. It rebuilds each sprint from the work items' history and checks the result against Jira's sprint records when the sprint closes. How the check works